You’re halfway through a job when the customer asks for something outside the estimate. A cleaner might discover an additional room, a mover might be asked to take a piano left off the inventory, or a contractor might open a wall and find damage that needs a separate repair. Before taking on the extra work, check the original estimate and give the customer a chance to approve any change in price or schedule.
1. Start with a defined original scope
Before work begins, describe what's included in the accepted estimate or service agreement. Be specific about quantities, service areas, materials, access requirements, and exclusions where relevant.
For a move, that may mean addresses, inventory assumptions, stairs, packing, and special items. For a cleaning job, it might mean rooms, tasks, and property condition. For construction, it may include plans, finishes, and assumptions about hidden conditions.
A detailed estimate gives both sides a record to consult when a request comes up or the crew finds an unexpected condition.
2. Pause before performing unapproved extra work
When a potential change appears, first determine whether it's already part of the original agreement. Correcting your own error generally isn't a legitimate reason to charge the customer extra.
For additional work, explain what you found and give the customer their options before continuing. If there’s a safety concern, secure the area and follow the procedures required for your trade.
You could say, “We found damage that wasn’t covered in the estimate. I can show you where it is, explain the repair options, and price the work before we go further.”
3. Put the change in writing
A simple change order should identify:
The original job or agreement.
The additional or revised work.
Why the change is needed or requested.
The price adjustment and any tax treatment.
Any impact on scheduling or completion dates.
Who is authorized to approve it, and how approval is recorded.
A short written document or an appropriately recorded digital approval may be sufficient for routine work, depending on the agreement and applicable law. More complex or regulated work may require formal contract procedures.
Do not assume the person present at the property can authorize charges on behalf of the customer or property owner.
4. Calculate the price before offering it
Consider a hypothetical additional repair:
Additional expense | Estimate |
|---|---|
Three hours of burdened labor | $225 |
Materials | $180 |
Extra travel and job costs | $45 |
Estimated incremental cost | $450 |
On a $600 quote, the work contributes $150 before any further overhead allocation. That is 25% of the added price in this example.
Use your own costs and allow for the risk of the additional work. Account for overhead that still needs to be covered and check that each expense appears only once.
Even with the crew already on-site, the extra hours may leave you less time for the next job.
5. Explain the effect on the schedule
Extra work can create more than an extra charge. It may change crew availability, material delivery, or the completion date.
Give the customer the revised completion date or range and tell them which parts of the schedule still hold. Check when the extra inspection or part can be arranged before committing to a date.
Record whether the customer can decline the change and which parts of the original job can go ahead if they do.
6. Keep the records together
Store the original estimate, the approved change, relevant photos, messages, and final invoice under the same job record.
If the customer later asks why the invoice changed, your team should be able to explain it without searching several messaging apps.
Protect customer privacy when taking photographs or collecting property information. Obtain permission when needed.

7. Learn from repeated changes
If the same type of change happens regularly, your quoting process may need improvement.
A mover repeatedly discovering extra inventory might need better pre-move questions. A cleaner repeatedly finding severe conditions might benefit from photos or a preliminary assessment. A contractor might need clearer allowances and exclusions.
Track how often jobs change, why they change, and whether your estimates consistently understate required work.
Check the final invoice
Before sending the invoice, compare every added line with the change order the customer approved. Include its reference in the invoice so the customer and your team can find the agreed price and scope.
